How long does a custom project take?

Almost every overrun has the same cause, and it is not development speed.

The real cause

Waiting for decisions, content, access or feedback. A developer waiting three days for an answer costs three calendar days without a line of code.

What you can do

Appoint one person who decides, with the mandate to do so. A project with four decision-makers and no clear hierarchy takes twice as long.

Budget for testing

Testing is not an end-of-project formality. That is where the surprises are, and it is the most underestimated phase.

Deliver in pieces

A project delivered in one go after six months is a gamble. Delivering in stages lets you correct course and see sooner what it actually becomes.

The practical rule

Ask your supplier what they need from you and when. A schedule containing only their own tasks is incomplete by design.